Power, Vol.150, No.7, 46-46, 2006
Nova Scotia Power's Point Aconi plant overcomes CFB design problems to become rock of reliability
Point Aconi's circulating fluidized-bed boiler experienced erosion, corrosion, and fouling problems from the day it went on-line in 1993. After several frustrating years of unreliable operation, in late 1999, Nova Scotia Power discovered the right combination of engineering and fuel modifications. Today, after a switch to 80% petroleum coke and major boiler modifications, Point Aconi's output exceeds its original nameplate rating. For having the vision and fortitude to plan and execute a multiyear, $20 million project to revitalize North America's first in-service utility CFB boiler, Nova Scotia Power's Point Aconi plant is the well-deserved winner of POWER magazine's 2006 Marmaduke Award for excellence in O&M. The award is named for Marmaduke Surfaceblow, the fictional marine engineer/plant troubleshooter par excellence.