International Journal of Energy Research, Vol.27, No.14, 1251-1263, 2003
Generation unit selection via capital asset pricing model for generation planning
The electric power industry in many parts of U.S.A. is undergoing substantial regulatory and organizational changes. Such changes introduce substantial financial risk in generation planning. In order to incorporate the financial risk into the capital investment decision process of generation planning, in this paper, we develop and analyse a generation unit selection process via the capital asset pricing model (CAPM). In particular, utilizing realistic data on gas-fired, coal-fired, and wind power generation units, we show which and how concrete steps can be taken for generation planning purposes. It is hoped that the generation unit selection process developed in this paper will help utilities in the area of effective and efficient generation planning when financial risks are considered. Copyright (C) 2003 John Wiley Sons. Ltd.